Building Permit (full)
Authorizes construction of a new building, an addition or a material alteration of a building or structure.
You need it when: You construct a new building, an addition, or materially alter a building or structure.
Why it's needed
- Required under the Building Code Act for most construction, demolition, additions and major renovations [TO].
- Also covers stacked site trailers, trailers without wheels or needing a water hook-up, and pedestrian bridges attached to a building.
When to apply
- Obtain before construction beyond shoring/excavation, or use part permits (shoring, foundation, superstructure) to start earlier.
- Large projects may get a conditional permit (Conditional Building Permit Agreement); the unconditional permit follows site plan approval.
- Plan for multiple review cycles. Review timelines apply per complete submission.
Review time
Plan for about 90 business days. OBC review for Part 3 large/complex buildings: 20–30 BD per complete submission [TO]; plan ~90 BD to allow for multiple cycles [Guide].
Documents for a complete application
- Completed Application for a Permit to Construct or Demolish (Ontario form) + Schedule 1 designer information for every design discipline
- Zoning Applicable Law Certificate (ZAP) or other confirmation of zoning compliance
- Evidence that other Applicable Law approvals are in place (e.g., Site Plan approval, TRCA permit, MTO Building & Land Use permit near provincial highways)
- Architectural, structural, mechanical, electrical and plumbing drawings, sealed by Ontario-licensed professionals
- Ontario Building Code data matrix / code analysis; fire-protection & life-safety report where applicable
- Geotechnical report (for foundations/shoring)
- Commitment to General Review by architect and engineer
- Electronic submission per Toronto Building's Electronic Submission Guidelines (PDF naming, sheet index)
- Toronto Building application checklist for the permit type (ask for the latest version at pre-application)
Submission checklists
How to submit
- Submit electronically to Toronto Building; confirm the channel at the pre-application meeting.
- Pay fees (calculated on the proposed work). EFT/credit card processes faster than cheque.
- Toronto Building confirms completeness (≈5–7 BD) before the review clock starts.
- Track status with the Building Application Status search.
Fees
Calculated per Municipal Code Ch. 363 based on building class and floor area.
Tips
- Book a pre-application meeting to confirm checklist items and submission logistics.
- Hold a regular (e.g., monthly) working group with Toronto Building on large programs [Plan].
Often needed first
- Site Plan Control / Site Plan Review
- Zoning Applicable Law Certificate (ZAP)
- MTO Building & Land Use Permit
Forms and guides
- Municipal Road Damage Deposit Declaration (Toronto Building) (City of Toronto, declaration)
- Application for a Permit to Construct or Demolish (City of Toronto, application form)
- Schedule 1: Designer Information (City of Toronto, application form)
- Commitment to General Reviews by Architect and Engineer (City of Toronto, declaration)
- Building Design Information Form (City of Toronto, application form)
- Vibration Control Form (City of Toronto, declaration)
- Declaration: Use of Zoning Applicable Law Certificate (City of Toronto, declaration)
- Tree Protection By-law Declaration (City of Toronto, declaration)
- Declaration: Overhead Electrical Conductors (City of Toronto, declaration)
- Toronto Building: Building Permit Guide (City of Toronto, guide)
Official pages
Track Building Permit (full) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.