MTO Building & Land Use Permit
MTO permit for structures near provincial highways.
You need it when: Structures above or below grade within MTO's permit control area (e.g., within 395 m of a 400-series highway centreline).
Why it's needed
- Required for building and land use within the highway corridor control area.
When to apply
- An Applicable Law item for building permits. MTO issues it to the party executing the work.
Review time
Plan for about 35 business days.
Documents for a complete application
- Site plan with setbacks to the highway
- Drainage/stormwater information
- Traffic impact where applicable
How to submit
- MTO Highway Corridor Management System (HCMS) online.
Official pages
Track MTO Building & Land Use Permit free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.