Permit Library › Municipal: City of Toronto › Toronto Water & Engineering & Construction Services › Sewer discharge (dewatering)

Private Water Discharge Permit: Short Term (construction dewatering)

Permit to discharge private water to City storm or sanitary/combined sewers, generally for 1 year or less [TO].

You need it when: You pump groundwater, runoff or precipitation into City sewers during construction.

Why it's needed

When to apply

Review time

Plan for about 30 business days.

Documents for a complete application

Submission checklists

How to submit

Fees

Storm: no fee (stricter limits). Sanitary/combined: volume-based fee [TO].

Often needed first

Forms and guides

Official pages

Track Private Water Discharge Permit: Short Term (construction dewatering) free.
Deadlines in business days, email alerts before decisions are due, and your whole team in one place.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.