EASR Registration: Water Taking (Construction Dewatering)
Online self-registration for mid-range construction dewatering (O. Reg. 63/16).
You need it when: Construction dewatering between 50,000 and 400,000 L/day.
Why it's needed
- Required instead of a PTTW for eligible construction dewatering in this range.
When to apply
- Registration is immediate once the Water Taking Plan and Discharge Plan are prepared. The 400,000 L/day limit applies per pit and its area of influence.
Review time
Immediate on online registration.
Documents for a complete application
- Water Taking Plan and Discharge Plan by a Qualified Person (O. Reg. 63/16)
How to submit
- Ontario EASR online registration.
Official pages
Track EASR Registration: Water Taking (Construction Dewatering) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.