Mississauga Storm Sewer Temporary Discharge Approval (dewatering)
Approval under the Storm Sewer Use By-law 0046-2022. Construction dewatering may go to a municipal storm sewer only with a valid permit and fees paid [MISS].
You need it when: Temporarily discharging groundwater or surface runoff (e.g. construction dewatering) to a Mississauga storm sewer.
Why it's needed
- All discharges to the City storm system must meet the Storm Sewer By-law to protect downstream water quality [MISS].
When to apply
- Before dewatering. The approval needs lab analysis of water samples; coordinating it takes about 1–2 weeks [MISS].
- Developments also sign the Storm Sewer Use By-law Acknowledgement covering City and Region of Peel dewatering requirements [MISS].
- Discharges to sanitary sewers go to the Region of Peel instead.
Review time
Plan for about 10 business days. about 1–2 weeks [MISS]
Documents for a complete application
- Storm Sewer Temporary Discharge Approval form [MISS]
- Laboratory results of water quality samples [MISS]
- Hydrogeological report / dewatering plan and treatment details
- Storm Sewer Use By-law Acknowledgement (developments) [MISS]
How to submit
- Email env.inquiries@mississauga.ca [MISS].
Forms and guides
- Mississauga Storm Sewer Temporary Discharge Approval Form (City of Mississauga, application form)
- Mississauga Storm Sewer Use By-law 0046-2022 (City of Mississauga, by-law)
Official pages
Track Mississauga Storm Sewer Temporary Discharge Approval (dewatering) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.