Plumbing and Site Services Permit: Water or Sewer Connection and Septic Decommissioning (King)
Building permit from the King Building Division for plumbing, municipal water and sewer connections, water upgrades and septic decommissioning, under Building By-law 2025-068 [king.ca].
Why is it needed?
- The Township's Building Permits page lists plumbing work as needing a building permit [king.ca].
- The Building Division issues the Municipal Services Connection, Water Connection or Upgrade, and Sewer Connection and Septic Decommissioning permit packages [king.ca].
When should you apply?
- New water, sanitary or storm connections are shown in the Development Engineering Approval submission, which comes before the building permit [king.ca].
- If the work occupies the municipal right-of-way, such as crossing the boulevard for service connections, email a Road Occupancy Permit application to Public Works at least 10 business days before you start [king.ca].
- New and replaced water meters must be inspected, usually at the insulation stage [king.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Water Connection or Upgrade Permit Application Forms Package [king.ca]
- Sewer Connection and Septic Decommissioning Application Forms Package [king.ca]
- Municipal Services Connection Permit Application [king.ca]
- Permit to Connect Sewers and Drains form [king.ca]
How do you submit it?
- Download the package from the Township's Forms & Applications page and apply to the Building Division on the CityView Portal at cityview.king.ca/Portal [king.ca].
- Book the water meter inspection with the Township at 905-833-5321 [king.ca].
What are the fees?
2026 fees: stand-alone plumbing $455.00 residential or $681.00 non-residential, municipal water, sanitary or storm connection $285.00 per trench (connection fee extra), septic decommissioning $285.00, septic-to-municipal conversion $341.00 [king.ca]. Water meters from Public Works cost $741.00 (3/4 inch) to $3,035.00 (2 inch) with HST [king.ca].
Forms and guides
- King Building By-law 2025-068 (Township of King, by-law)
- King 2026 Fees and Charges (Township of King, fee schedule)
Official pages
- Forms and applications
- Development Engineering Approval
- Road Occupancy Permit
- 2026 Fees and Charges (PDF)
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.