Building Permit: Large Building, Part 3 (King)
Construction permit under King Building By-law 2025-068 for a Part 3 building, such as a larger commercial, institutional or apartment building [king.ca].
You need it when: You build, add to or alter a large commercial, institutional, industrial or multi-residential building in the Township of King that falls under Part 3 of the Building Code.
Why is it needed?
- Building By-law 2025-068 requires a construction permit application on the provincial form, with complete plans and the fees in the Fees and Charges By-law [king.ca].
- Where the Building Code requires an architect or engineer to review construction, the application needs their general review undertaking [king.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Where Site Plan Control or a site plan or subdivision agreement applies, the application is not complete until the agreement's building permit conditions are cleared [king.ca].
- Permits or written approvals for road cuts, culverts, driveway entrances, conservation authority, site servicing and other applicable law must be in place before the permit is issued [king.ca].
- To start before the full permit is issued, ask about a conditional permit or a partial permit for footings and foundations [king.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (provincial form) [king.ca]
- Complete plans and specifications that follow the Electronic Building Permit Application Submission Standards [king.ca]
- Commitment to General Review form [king.ca]
- Qualified designer form [king.ca]
- Site and grading plan [king.ca]
How do you submit it?
- Apply to the Building Division on the Township's CityView Portal at cityview.king.ca/Portal [king.ca].
What are the fees?
2026 fees: Groups A and B finished $21.00 per m2, shell $13.00 per m2 and fit-out $8.00 per m2 (minimum $400), multi-residential $23.00 per m2 (minimum $3,000), Groups D and E finished $20.00 per m2 (shell $12.00), Group F $13.00 per m2 (shell $10.00) [king.ca].
Forms and guides
- King Building By-law 2025-068 (Township of King, by-law)
- King 2026 Fees and Charges (Township of King, fee schedule)
Official pages
Track Building Permit: Large Building, Part 3 (King) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.