Permit Library › Municipal: City of Toronto › Transportation Services › Road cuts & encroachments
Tie-backs, Piling & Shoring Agreement
Agreement required when tie-back systems or shoring are in the public right-of-way.
You need it when: Tie-backs or shoring extend under the public right-of-way.
Why it's needed
- Required for tie-backs/shoring within the City right-of-way.
When to apply
- Before installing tie-backs; needed for the shoring permit.
- If anchors extend beyond the right-of-way into lanes or private property, get written permission from all affected owners first.
Review time
Plan for about 20 business days.
Documents for a complete application
- Shoring/tie-back drawings showing ≥1.0 m clearance from trunk watermains/sewers, including the grout bulb
- Written consents from adjacent property owners where tie-backs cross property lines
- Insurance / indemnity
Submission checklists
How to submit
- Transportation Services, Right-of-Way Management.
Forms and guides
- Transportation Services Permit Application (street occupation, construction staging, encroachments) (City of Toronto, application form)
- Construction Encroachments Permit Application (City of Toronto, application form)
- Municipal Code Chapter 743: Streets and Sidewalks, Use of (City of Toronto, by-law)
Official pages
Track Tie-backs, Piling & Shoring Agreement free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.