Occupancy Permit (partial / full)
Permission to occupy an unfinished building.
You need it when: You need to occupy all or part of a building before it is complete.
Why it's needed
- Needed where facilities must be occupied while construction continues.
When to apply
- Near the end of construction. Requires inspections and operational life-safety systems.
Review time
Plan for about 30 business days.
Documents for a complete application
- Occupancy checklist
- Fire alarm/sprinkler verification letters
- General review letters from designers
Submission checklists
How to submit
- Request through Toronto Building inspections.
Forms and guides
- Authority to Occupy Request (City of Toronto, application form)
Official pages
Track Occupancy Permit (partial / full) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.