Zoning Certificate (King)
A Zoning Certificate from the King Planning Division, a zoning review that must be approved before you apply for a building permit, Development Engineering Approval or pool permit [king.ca].
Why is it needed?
- You need a Zoning Certificate to apply for a pool permit [king.ca].
- Development Engineering requires the approved Zoning Certificate and stamped drawings before you submit for engineering approval [king.ca].
- King does not process a building permit application further until zoning approvals are confirmed (Building By-law 2025-068 s. 7.1.1) [king.ca].
When should you apply?
- Get the Zoning Certificate first, then Development Engineering Approval, then apply for the building permit [king.ca].
- If the engineering approval changes anything that affects zoning, you need a new Zoning Certificate [king.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Application for Zoning Certificate (fillable PDF) [king.ca]
How do you submit it?
- Apply through the Township Zoning Certificate page at king.ca/ZoningCertificate [king.ca].
What are the fees?
2026 fee: $66.00 for an accessory building, $132.00 for a new house or addition, $198.00 for a non-house building up to 300 m2, $329.00 over 300 m2, $66.00 for a driveway, landscaping or site alteration and $66.00 for a swimming pool (2026 Fees and Charges, effective January 5, 2026) [king.ca]. 2026 fee: $153.00 for a zoning approval and clearance [king.ca].
Forms and guides
- King 2026 Fees and Charges (Township of King, fee schedule)
- King Application for Zoning Certificate (Township of King, application form)