Permit Library › Other GTA municipalities › Township of King › Planning applications, heritage and Committee of Adjustment (Planning Division)

Site Plan Approval (King)

Site plan approval from the King Planning Division under section 41 of the Planning Act, with agreement conditions to clear before a building permit [king.ca].

You need it when: Your development in King is subject to site plan control under section 41 of the Planning Act.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 43 business days. Planning Act, R.S.O. 1990, c. P.13, s. 41(12) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fees: complex residential $20,400.00 plus $357.00 per unit, simple $10,200.00, Oak Ridges Moraine or Greenbelt simple $1,530.00, complex joint $2,550.00, and site plan exemption or clearance $408.00 (2026 Fees and Charges) [king.ca].

Forms and guides

Official pages

Track Site Plan Approval (King) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.