Road Occupancy Permit, including Construction Parking and Bins (King)
Road Occupancy Permit from King Public Works under By-law 2020-061 for construction work, bins, storage or vehicle parking in the municipal right-of-way [king.ca].
Why is it needed?
- A Road Occupancy Permit is required before a demolition, renovation or construction project temporarily occupies any portion of the municipal right-of-way [king.ca].
- It can be needed for work on private property when vehicles, equipment, bins or materials sit in the right-of-way, including crossing the boulevard for driveway, pool or service connection work [king.ca].
When should you apply?
- Submit the application at least 10 business days before your start date, and notify the Township 48 hours before work starts [king.ca].
- Get Ontario One Call locates, keep the permit on site, and finish all work including restoration before the permit expires or re-apply [king.ca].
- For emergency work, apply within 24 hours or as soon as the emergency is managed, and for York Region roads get a Region road use permit [king.ca].
How long does review take?
Plan for about 10 business days. minimum lead time [king.ca]
What documents does a complete application need?
- Road Occupancy-Road Closure Application, FORM-PW-106 [king.ca]
- Drawing or sketch of the work in the right-of-way [king.ca]
- Pre-construction photos, not Google images [king.ca]
- Certificate of insurance naming the Township, with at least $5,000,000 liability [king.ca]
- Traffic control plan under OTM Book 7, if a lane or shoulder is occupied [king.ca]
How do you submit it?
- Email form FORM-PW-106 to utilities@king.ca with the subject "ROP Application" and the address [king.ca].
- Public Works reviews the application [king.ca].
What are the fees?
2026 fee: $318.00 for a short duration Road Occupancy Permit, $790.00 per road for a long duration permit and $82.00 per week for an extension (2026 Fees and Charges, Schedule E) [king.ca]. Rush applications with under 2 business days notice pay the permit fee plus 30%, and work started before applying pays the fee plus 50% [king.ca]. The security deposit is set at the Township's discretion, with a minimum of $5,000.00, and is returned after the restoration is inspected and accepted [king.ca].
Forms and guides
- King 2026 Fees and Charges (Township of King, fee schedule)
- King Road Occupancy-Road Closure Application (FORM-PW-106) (Township of King, application form)
Official pages
- Road occupancy permit
- Road Occupancy-Road Closure Application FORM-PW-106 (PDF)
- Road Occupancy and Road Closure By-law 2020-061 (PDF)
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.