Pool Permit and Pool Enclosure (King)
Township of King pool permit for the pool and its enclosure, reviewed against Fence By-law 2012-132 with a grading and drainage plan [king.ca].
Why is it needed?
- The Township says a pool permit is required in order to have a pool in King [king.ca].
- The pool enclosure must meet Fence By-law 2012-132, and Public Works inspects the enclosure, grading and any road damage before the security deposit is released [king.ca].
When should you apply?
- Get a Zoning Certificate before you apply for the pool permit [king.ca].
- The enclosure inspection must be completed before any water is placed in the pool, and all grading must be complete before the deposit is released [king.ca].
- In a TRCA or LSRCA regulated area, get the conservation authority permit or written confirmation that none is needed, and on the Oak Ridges Moraine a Site Plan Development application may be needed [king.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Site plan or survey with pool and equipment setbacks and hard surface areas in m2 [king.ca]
- Pool enclosure drawings under Fence By-law 2012-132, or photos if existing [king.ca]
- Grading and drainage plan with geodetic elevations, swales and slopes [king.ca]
- Pre-construction photos of the road allowance, construction access and neighbouring infrastructure [king.ca]
- Contractor general liability insurance [king.ca]
- Developer and consultant approval, in an unassumed subdivision [king.ca]
How do you submit it?
- Apply on the CityView Portal using the Township's step-by-step guide, or on online form FORM-PW-115 [king.ca].
- Send questions and Public Works inspection requests to poolpermit@king.ca [king.ca].
What are the fees?
2026 fee: $870.00 for an in-ground or on-ground pool and $250.00 for an above-ground pool (2026 Fees and Charges) [king.ca]. The Pool Permit Requirements 2025 checklist sets security deposits of $5,000.00 for an in-ground pool enclosure and $1,000.00 for an above-ground pool [king.ca]. 2026 fee: $280.00 re-inspection, $175.00 extension, $66.00 for the pool Zoning Certificate, double fees for work without a permit, and a $500 non-compliance fee at final inspection [king.ca].
Forms and guides
- King 2026 Fees and Charges (Township of King, fee schedule)
- King Application for Zoning Certificate (Township of King, application form)
- King Pool Permit Requirements 2025 (Township of King, checklist)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.