Municipal Consent for Utility Work (King)
Municipal Consent from King Public Works for new, upgraded or relocated utility infrastructure in the Township right-of-way, valid for one year [king.ca].
You need it when: You install, upgrade or relocate utility infrastructure in a King Township right-of-way.
Why is it needed?
- The Township requires Municipal Consent for new, upgraded or relocated utility infrastructure in the right-of-way [king.ca].
- The consent is valid for one year, after which an MC Extension is needed [king.ca].
When should you apply?
- A Road Occupancy Permit is also required for the work in the right-of-way [king.ca].
- The Township asks for Road Occupancy Permit applications at least 10 business days before the start date [king.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Drawings of the proposed utility work [king.ca]
- Road Occupancy-Road Closure Application, FORM-PW-106 [king.ca]
How do you submit it?
- Email the drawings to utilities@king.ca for Public Works [king.ca].
What are the fees?
2026 fee: $490.00 for a simple Municipal Consent and $624.00 for a comprehensive one (2026 Fees and Charges, Schedule E) [king.ca].
Forms and guides
- King 2026 Fees and Charges (Township of King, fee schedule)
Official pages
Track Municipal Consent for Utility Work (King) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.