Minor Variance (King)
A minor variance from the King Zoning By-law, decided by the Committee of Adjustment under section 45 of the Planning Act [ON].
Why is it needed?
- The Committee of Adjustment hears minor variance applications, with separate 2026 fees for small, major and as-built variances [king.ca].
- A Hard Landscaping Exemption Permit covers excess hardscape only and does not replace the need for a minor variance [king.ca].
When should you apply?
- Complete Step 1, the Committee of Adjustment zoning review, and Step 2, the pre-consultation meeting, or file the waivers, before you submit the application [king.ca].
- Where a minor variance is needed, building permit review timelines do not start until the variance is approved, the appeal period has lapsed and the decision is final and binding (Building By-law 2025-068 s. 3.3) [king.ca].
How long does review take?
Plan for about 21 business days. Planning Act, R.S.O. 1990, c. P.13, s. 45 [ON]
What documents does a complete application need?
- Minor Variance Application (fillable PDF) [king.ca]
- COA Step 1 Zoning Review Application, or its waiver [king.ca]
- COA Step 2 Pre-Consultation Meeting Application, or its waiver [king.ca]
- Owner Agent Authorization Form, if an agent applies [king.ca]
How do you submit it?
- Apply to the Township Committee of Adjustment, whose meeting details are on the Committee of Adjustment page [king.ca].
What are the fees?
2026 fee: $2,589.00 for a minor variance for accessory buildings, pools and additions under 50 m2, $4,017.00 for a major variance and $4,590.00 for an as-built variance (2026 Fees and Charges, effective January 5, 2026) [king.ca]. 2026 fee: $204.00 for the CAP pre-consultation for a minor variance [king.ca]. Applications that arise from by-law enforcement pay the fee plus 50% [king.ca].
Forms and guides
- King 2026 Fees and Charges (Township of King, fee schedule)
- King COA Zoning Review Application and Waiver (Township of King, application form)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.