Consent to Sever, Easement or Lot Addition (King)

Consent from the King Committee of Adjustment to sever land, add land to a lot or grant an easement, under section 53 of the Planning Act [ON].

You need it when: You want to sever a lot, add land to a neighbouring lot or create an easement in King.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 64 business days. Planning Act, R.S.O. 1990, c. P.13, s. 53(14) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $7,975.00 for a consent application (2026 Fees and Charges, effective January 5, 2026) [king.ca]. Applications that arise from by-law enforcement pay the fee plus 50% [king.ca].

Forms and guides

Official pages

Track Consent to Sever, Easement or Lot Addition (King) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.