Permit Library › Other GTA municipalities › Region of York › Regional roads
York Region Load Exemption Permit
York Region road-use permit, applied for through the online road permit portal [york.ca].
You need it when: Heavy vehicles on York Region road sections under reduced load (e.g. spring half-load) restrictions.
Why it's needed
- Required for this activity on a York Region road [york.ca].
When to apply
- Apply about 3 weeks before the start [york.ca].
Review time
Plan for about 10 business days. apply 3 weeks ahead [york.ca]
Documents for a complete application
- Certificate of insurance on the Region's form, signed and stamped by the broker, valid for the whole permit [york.ca]
- Traffic management plan [york.ca]
- Road sections to be used [york.ca]
How to submit
- York Region road permit portal (roadpermits.york.ca); permits@york.ca, 1-877-464-9675 ext. 75700 [york.ca].
Fees
$580 permit, $300 per revision, $220 re-inspection; road closure, peak-hour and pavement degradation fees where they apply [york.ca]. A security deposit is required [york.ca].
Official pages
Track York Region Load Exemption Permit free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.