Building Permit: Large Building, Part 3 (Whitchurch-Stouffville)
Non-residential building permit from the Town's Building Services for a Part 3 building, with fees in Fees and Charges By-law 2021-112-FI [townofws.ca].
Why is it needed?
- The Town's non-residential permits cover industrial, commercial and institutional buildings [townofws.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- Site Plan Control Areas, TRCA or LSRCA regulated areas and MTO highway corridors are applicable law that must be met to receive a building permit [townofws.ca].
When should you apply?
- Clear site plan control and any TRCA, LSRCA or MTO approval before the building permit can issue [townofws.ca].
- Check the Zoning By-law first, since it applies to every project. The Zoning and Applicable Laws page links a Preliminary Zoning Review [townofws.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish [townofws.ca]
- Applicable Law Checklist, which every building permit application must include [townofws.ca]
- Proof of compliance with applicable law, such as site plan or conservation authority approval [townofws.ca]
- Completed general designer's schedule [townofws.ca]
How do you submit it?
- Apply through the Application and Permit Portal at cityviewportal.townofws.ca, or email the application to buildingpermits@townofws.ca [townofws.ca].
- Residential apartments and stacked townhouses are applied for at the Building and Planning Counter, 111 Sandiford Drive [townofws.ca].
- Building Services: buildingpermits@townofws.ca, (905) 640-1900 ext. 2249, Building and Planning Counter, 111 Sandiford Drive [townofws.ca].
What are the fees?
Fees are set in Schedule E of Fees and Charges By-law 2021-112-FI [townofws.ca]. It requires a $5,000 minimum down payment for classes other than new single, semi and town-style homes where the estimated fee exceeds $5,000, and down payments are not refunded [townofws.ca]. Refunds are 75%, 60%, 45% or 35% depending on how far processing went, and a maintenance fee of 10% per year ($200 minimum) applies if the final inspection is not done 3 years after issuance [townofws.ca].
Forms and guides
- Whitchurch-Stouffville Application for a Permit to Construct or Demolish (Town of Whitchurch-Stouffville, application form)