Permit Library › Municipal: City of Toronto › Toronto Water & Engineering & Construction Services › Connections & hydrants
Watermain Shut-off / Valve Operation & Temporary Relocation (Toronto Water)
Toronto Water operates all City valves. Planned turn-offs and valving are requested from Toronto Water; temporary or emergency relocations are requested from Toronto Water Operations with the reason, affected area and duration.
You need it when: Your work needs City watermain valves operated, a planned water shut-off, a temporary bypass, or an unplanned relocation of a watermain or sewer.
Why it's needed
- Only Toronto Water may operate City watermain valves [TO].
- Contractors must notify affected property owners first [TO].
When to apply
- Request valving at least 2 working days in advance (TS 7.70) [TO]; larger shutdowns need a Construction Sequencing and Watermain Shut Plan agreed in design.
- Work near transmission mains needs a Toronto Water inspector and at least 2 weeks' notice.
Review time
Plan for about 2 business days. Minimum 2 working days' notice for valving [TO].
Documents for a complete application
- Shut-off request with location, valves, date/time and duration
- Construction Sequencing and Watermain Shut Plan (for planned shutdowns)
- Notice to affected owners
- For relocations: reason, impacted areas and duration
How to submit
- Planned turn-on/off by contractors: Toronto Water, Central Services [TO]. Emergencies: 311.
Official pages
Track Watermain Shut-off / Valve Operation & Temporary Relocation (Toronto Water) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.