Site Plan Approval (Whitby)
Site plan approval from Town of Whitby Planning and Development, which you may need before a building permit when the property is subject to site plan control [whitby.ca].
You need it when: Your Whitby property is subject to site plan control and you plan to build on it or add to it.
Why is it needed?
- The Building Permits page says that if a property is subject to site plan control, you may have to apply for site plan approval [whitby.ca].
- Site plan control comes from section 41 of the Planning Act [ON].
When should you apply?
- Apply for site plan approval before the building permit, as one of the approvals to check before you apply [whitby.ca].
- Pre-approved model registrations for builder houses need a valid site plan or subdivision number [whitby.ca].
How long does review take?
Plan for about 43 business days. Planning Act, R.S.O. 1990, c. P.13, s. 41(12) [ON]
How do you submit it?
- Apply to Town of Whitby Planning and Development as set out on the Town's Site Plan Approval page [whitby.ca].
Official pages
Track Site Plan Approval (Whitby) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.