Building Permit: New House, Addition, Additional Dwelling Unit or Finished Basement (Whitby)
Building permit from Whitby Building Services for a new house, addition, additional dwelling unit (ADU) or finished basement, required under the Building Code Act [ON].
You need it when: You build a new house, an addition, an additional dwelling unit or a finished basement in Whitby, or make structural changes such as new windows, doors, walls or a walkout.
Why is it needed?
- The Town requires a permit for new homes, additions, finished basements, additional dwelling units, new windows or doors, adding or removing walls, and basement or main floor walkouts [whitby.ca].
- Re-cladding may need a permit where it changes the structure, makes a significant material change such as vinyl to brick or stone veneer, or affects how the wall assembly performs [whitby.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Confirm the work meets the Zoning By-law first, because a proposal that does not comply may need a minor variance from the Committee of Adjustment [whitby.ca].
- Approvals from CLOCA, Town Heritage, Town Engineering (Grading, Servicing and Drainage Permit), the Ministry of Transportation or the Region of Durham may be needed before you apply [whitby.ca].
- Incomplete submissions may delay the entire approval process [whitby.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish (Feb 2026) [whitby.ca]
- Schedule 1: Designer Information Form [whitby.ca]
- Architectural drawings, plus grading, structural, engineered floor and roof, and HVAC drawings where they apply [whitby.ca]
- Applicable Law Checklist [whitby.ca]
- Letter of Authorization, if an agent applies for the owner [whitby.ca]
- Region of Durham Health Department approval for a septic system, and a CLOCA permit, where they apply [whitby.ca]
How do you submit it?
- Apply on the E-Portal at portal.whitby.ca (strongly preferred for an ADU), by email to buildingpermits@whitby.ca, or on paper at Building Services Division, 3050 Garden St. Unit 102, Whitby ON L1R 2G7 [whitby.ca].
- Every submission is pre-screened, then next steps and an invoice for credit card payment are emailed [whitby.ca].
What are the fees?
2026 fees: $22.37 per m2 for a new house or addition (BGP-6) and $10.65 per m2 for an ADU alteration or other low-rise residential alteration (BGP-10, BGP-11), with a $305.00 minimum (2026 Building Permit Fees, Schedule N to By-law 7220-17) [whitby.ca].
Forms and guides
- Whitby 2026 Building Permit Fees (Schedule N to By-law 7220-17) (Town of Whitby, fee schedule)
- Whitby Application for a Permit to Construct or Demolish (Feb 2026) (Town of Whitby, application form)
- Whitby Applicable Law Checklist (Town of Whitby, checklist)
- Whitby Letter of Authorization (Town of Whitby, application form)
- Whitby E-Portal Building Permit Type Definitions (Town of Whitby, guide)
- Whitby E-Portal Documentation Required (Residential) (Town of Whitby, checklist)
- Whitby E-Portal Submission Standards (Town of Whitby, guide)
Official pages
Track Building Permit: New House, Addition, Additional Dwelling Unit or Finished Basement (Whitby) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.