Zoning By-law Amendment (Vaughan)

A site-specific amendment to the Zoning By-law under section 34 of the Planning Act, processed by Development and Parks Planning and decided by Council [vaughan.ca].

You need it when: Your Vaughan project needs a use, height, parking or other standard that the Zoning By-law does not allow.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 64 business days. Planning Act, R.S.O. 1990, c. P.13, s. 34(11) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $11,307 base plus tiered per-unit charges of $787, $293, $89 and $39, to a maximum of $95,669, for residential applications (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $4,772 per hectare plus $0.48 per m2 for non-residential applications (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $4,760 approval surcharge if the amendment is approved (Fees and Charges By-law 051-2026) [vaughan.ca].

Forms and guides

Official pages

Track Zoning By-law Amendment (Vaughan) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.