Draft Plan of Subdivision (Vaughan)
Draft plan of subdivision approval under section 51 of the Planning Act, processed by Development and Parks Planning and decided by Council [vaughan.ca].
Why is it needed?
- A draft plan of subdivision is required when dividing land into more than three parcels and creates development blocks, public streets, parks and services [vaughan.ca].
- Since Bill 23 (More Homes Built Faster Act, 2022) there is no Public Meeting; a Technical Report goes to Committee of the Whole and then Council [vaughan.ca].
- Under section 51(34) of the Planning Act, the applicant may appeal to the Ontario Land Tribunal if the approval authority fails to make a decision on a draft plan of subdivision within 120 days after the application is received [ON].
When should you apply?
- An optional pre-application consultation (PAC) meeting comes first and identifies what a complete application needs [vaughan.ca].
- The City sends a Notice of Complete Application to the landowner within 30 days of receipt and to the public within 15 days after that, or a Notice of Incomplete Application within 30 days [vaughan.ca].
- Keep the public notification sign up until 7 days after the final decision [vaughan.ca].
- After draft approval, get a subdivision grading permit from Development Engineering before any building permit in the new subdivision [vaughan.ca].
- Development Engineering prepares the Subdivision Agreement from the draft approval conditions [vaughan.ca].
- The Notice of Decision goes out within 15 days of Council's decision and starts a 20-day appeal period; with no appeal, draft approval is in force from the Council approval date [vaughan.ca].
- The plan is then registered at the Land Registry Office [vaughan.ca].
How long does review take?
Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34) [ON]
What documents does a complete application need?
- Development Application Form, commissioned, which the City requires for all Planning Act applications [vaughan.ca]
- GIS Conformity Letter, which Planning GIS and Analytics emails back after you send your georeferenced digital drawings before the formal submission [vaughan.ca]
- Draft plan, drawings, reports and other materials for a complete application [vaughan.ca]
- Subdivision Agreement, prepared by Development Engineering after draft approval [vaughan.ca]
How do you submit it?
- Online through the Citizen Service Online Portal, which receives Planning Act applications; let the Planning Technician know when you submit [vaughan.ca].
- Pay the fee by cheque to the City, delivered to the City Hall Welcome Desk or mailed; the application is not processed until the cheque is received and the fee confirmed [vaughan.ca].
- Development and Parks Planning: developmentplanning@vaughan.ca, 905-832-2281, City Hall Level 200 [vaughan.ca].
What are the fees?
2026 fee: $61,904 base plus tiered per-unit charges of $879, $440, $133 and $39, to a maximum of $168,826, for residential plans (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $2,818 per hectare for non-residential land and $24,018 for each additional phase (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: subdivision grading permit of $630 for singles and semis and $384 per street townhouse unit (Fees and Charges By-law 051-2026) [vaughan.ca].
Forms and guides
- Vaughan Development Planning Application form (July 2023) (City of Vaughan, application form)
Official pages
- Draft Plan of Subdivision application
- Development application submission process
- Development Application Form (PDF)
- 2026 Development Application Fee Calculator
- Fees and Charges By-law 051-2026 (PDF)