Right-of-Way Occupation for Construction Staging (Vaughan)
Road Occupancy Permit under Road Allowance By-law 126-2024 for construction staging in the City road allowance, such as a bin or stored materials [vaughan.ca].
Why is it needed?
- A Road Occupancy Permit is needed for temporary storage of bins or materials in the road allowance, sidewalk obstruction, temporary lane occupancy, and crossing a boulevard for site access where there is no paved driveway [vaughan.ca].
- A bin in front of a property needs a Road Occupancy Permit if it sits in the road allowance, even if the sidewalk or boulevard is not affected [vaughan.ca].
When should you apply?
- Road Occupancy Permit applications must be submitted at least 10 business days before the proposed start date [vaughan.ca].
- Road Occupancy Permits are only approved for assumed roads [vaughan.ca].
- Request an extension through Service Vaughan before the permit expires, for up to 30 days, or a new application is needed [vaughan.ca].
- Restoring the road allowance to its original condition is the permit holder's responsibility [vaughan.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Certificate of insurance for $5,000,000 public liability naming the City as additional insured [vaughan.ca]
- Traffic control plan following Ontario Traffic Manual Book 7 [vaughan.ca]
- Sketches or drawings of the occupied area [vaughan.ca]
How do you submit it?
- Apply through Service Vaughan, the City's online portal for road permits [vaughan.ca].
- Utility Coordinator, Transportation and Fleet Management Services: Utility.Coordinator@vaughan.ca, 905-832-2281 [vaughan.ca].
What are the fees?
2026 fee: $355 for a simple short-duration Road Occupancy Permit (1 to 59 days) and $505 for a simple long-duration permit (60 to 365 days) (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $124 rush review (not guaranteed), $93 extension of up to 30 days, and $350 plus the regular fee for work started without a permit (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: Development Engineering's schedule also lists boulevard occupancy at $3 per m2 per month and roadway occupancy at $12 per m2 per month (Fees and Charges By-law 051-2026) [vaughan.ca].
Official pages
- Road permits
- Road occupancy permit terms (PDF)
- Certificate of insurance form (PDF)
- Road Allowance By-law 126-2024 (PDF)
- Fees and Charges By-law 051-2026 (PDF)