Right-of-Way Occupation for Construction Staging (Vaughan)

Road Occupancy Permit under Road Allowance By-law 126-2024 for construction staging in the City road allowance, such as a bin or stored materials [vaughan.ca].

You need it when: You occupy part of a Vaughan road allowance for construction staging, such as a bin, stored materials or construction equipment on City land.

Why is it needed?

When should you apply?

How long does review take?

No review time is published for this permit; ask the City when you apply.

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $355 for a simple short-duration Road Occupancy Permit (1 to 59 days) and $505 for a simple long-duration permit (60 to 365 days) (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $124 rush review (not guaranteed), $93 extension of up to 30 days, and $350 plus the regular fee for work started without a permit (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: Development Engineering's schedule also lists boulevard occupancy at $3 per m2 per month and roadway occupancy at $12 per m2 per month (Fees and Charges By-law 051-2026) [vaughan.ca].

Official pages

Track Right-of-Way Occupation for Construction Staging (Vaughan) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.