Temporary Road Closure (Vaughan)
Road Closure Application to Vaughan Transportation and Fleet Management Services for a full closure of a municipal roadway for construction or development [vaughan.ca].
Why is it needed?
- A permit is required when working within the City's road allowance, and full closures of municipal roadways for construction or development use the Road Closure Application [vaughan.ca].
- Partial lane closures use a Road Occupancy Permit instead, and road closures for events go through the Special Events Permit [vaughan.ca].
- A full closure lasting 14 days or more may need a report to Council [vaughan.ca].
When should you apply?
- The application must be submitted a minimum of 20 business days before the proposed start date [vaughan.ca].
- Road closures can be extended through Service Vaughan before the permit expires; once a permit expires, a new application is needed [vaughan.ca].
How long does review take?
Plan for about 20 business days. minimum lead time [vaughan.ca]
What documents does a complete application need?
- Justification letter for the closure [vaughan.ca]
- Traffic management or detour plan [vaughan.ca]
- Copy of the community notification letter [vaughan.ca]
- Engineering drawings [vaughan.ca]
- Certificate of insurance for $5,000,000 [vaughan.ca]
- WSIB clearance valid for the whole closure [vaughan.ca]
- Permit fee and any other documents the City asks for [vaughan.ca]
How do you submit it?
- Apply through the Service Vaughan online portal, which has a user manual [vaughan.ca].
- Questions go to the Utility Coordinator, Transportation and Fleet Management Services, Joint Operations Centre, 2800 Rutherford Rd., Utility.Coordinator@vaughan.ca or 905-832-2281 [vaughan.ca].
What are the fees?
2026 fee: $6,454.50 for a road closure request, payable on approval, plus consultation costs, and $3,090 for a road closure amendment (Fees and Charges By-law 051-2026) [vaughan.ca]. The road permits page instead lists a full closure under the complex road occupancy fee: 2026 fee: $2,333 for 1 to 13 days or $3,157 for 14 days or more (Fees and Charges By-law 051-2026) [vaughan.ca].
Forms and guides
- Vaughan Road Allowance By-law 126-2024 (consolidated) (City of Vaughan, by-law)
- Vaughan Road Closure Request form (City of Vaughan, application form)
Official pages
- Road permits
- Road closure terms and conditions (PDF)
- Certificate of insurance form (PDF)
- Sample traffic control plans (PDF)
- Service Vaughan portal user manual (PDF)
- Road Allowance By-law 126-2024 (PDF)
- Fees and Charges By-law 051-2026 (PDF)
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.