Permit Library › Other GTA municipalities › City of Vaughan › Building permits (Building Standards)
Occupancy Permit (Vaughan)
Occupancy permit under Vaughan Building By-law 168-2024, with an occupancy inspection after the notice of completion is served [vaughan.ca].
You need it when: You want to occupy a building or part of a building in Vaughan after construction, including each stage of partial occupancy.
Why is it needed?
- The City carries out an occupancy inspection after the notice of completion is served [vaughan.ca].
When should you apply?
- Building By-law 168-2024, Schedule B: the occupancy inspection is conducted within 10 days after the notice of completion is served; Saturdays, holidays and City closure days are not counted [vaughan.ca].
- A separate application is made for each stage of partial occupancy [vaughan.ca].
How long does review take?
Plan for about 10 business days. Building By-law 168-2024, Schedule B (City of Vaughan)
What documents does a complete application need?
- Occupancy permit application for each stage of occupancy [vaughan.ca]
- Notice of completion served on the City, which starts the occupancy inspection (Building By-law 168-2024, Schedule B) [vaughan.ca]
How do you submit it?
- Building inspections: buildinginspections@vaughan.ca, 905-832-8511 [vaughan.ca]
- Building Standards: buildingstandards@vaughan.ca, 905-832-8510 [vaughan.ca]
What are the fees?
See the City's 2026 Fees and Charges By-law 051-2026 [vaughan.ca].
Forms and guides
- Vaughan Building By-law 168-2024 (City of Vaughan, by-law)
Official pages
Track Occupancy Permit (Vaughan) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.