Dewatering Discharge Approval (Vaughan)

Discharge approval from the City of Vaughan under Sewer Use By-law 025-2024 for private water or wastewater, such as construction dewatering, sent to the City's storm or sanitary sewers; York Region approval is also needed [vaughan.ca].

You need it when: You will discharge construction dewatering, groundwater, stormwater or other private water or wastewater into a City of Vaughan storm or sanitary sewer.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 40 business days. minimum lead time [vaughan.ca]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $2,030 for a dewatering discharge permit and $1,310 for an extension (Fees and Charges By-law 051-2026) [vaughan.ca]. A sampling fee applies on confirmed non-compliance, and sanitary discharges carry a volumetric charge that is invoiced [vaughan.ca].

Official pages

Track Dewatering Discharge Approval (Vaughan) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.