Permit Library › Other GTA municipalities › City of Vaughan › Water, sewers and dewatering
Dewatering Discharge Approval (Vaughan)
Discharge approval from the City of Vaughan under Sewer Use By-law 025-2024 for private water or wastewater, such as construction dewatering, sent to the City's storm or sanitary sewers; York Region approval is also needed [vaughan.ca].
You need it when: You will discharge construction dewatering, groundwater, stormwater or other private water or wastewater into a City of Vaughan storm or sanitary sewer.
Why is it needed?
- Discharging private water or wastewater, including construction dewatering of groundwater and stormwater, into the City's storm or sanitary sewers needs a discharge approval from the City under Sewer Use By-law 025-2024 [vaughan.ca].
- The same discharge also needs approval from York Region through the York sewer use portal [vaughan.ca].
- Inspections are done by By-law and Compliance, Licensing and Permit Services [vaughan.ca].
When should you apply?
- Apply online a minimum of eight to 12 weeks before planned discharges are required; applications must be received a minimum of eight weeks prior to water or wastewater discharge [vaughan.ca].
- Incomplete applications are not accepted and delay the timeline [vaughan.ca].
- For a temporary discharge, after approval email waterandsewerbylaw@vaughan.ca at least five days ahead to book a site inspection and witness sampling [vaughan.ca].
- For a permanent discharge, after approval send sample results and flow meter details to waterandsewerbylaw@vaughan.ca and dischargeapprovals@vaughan.ca, allow up to two weeks, and do not discharge until authorized [vaughan.ca].
- Renewals can be made from two months before expiry, and amendments until two months before expiry [vaughan.ca].
How long does review take?
Plan for about 40 business days. minimum lead time [vaughan.ca]
What documents does a complete application need?
- Cover letter, letter of authorization and the City's document checklist [vaughan.ca]
- City standard certificate of insurance [vaughan.ca]
- MECP approval: an EASR letter for a temporary discharge, or a Permit to Take Water where the daily taking exceeds the threshold [vaughan.ca]
- TRCA written confirmation of no objection, or deferral to the City [vaughan.ca]
- Dewatering plan marked on P.Eng-sealed drawings showing collection and discharge points, treatment, piping, flow meter and sampling port [vaughan.ca]
- Hydrogeological report by a P.Geo with average and maximum discharge and water quality results [vaughan.ca]
- Two emergency contacts and equipment specifications [vaughan.ca]
- Temporary discharge: P.Eng memorandum on downstream sewer capacity [vaughan.ca]
- Permanent discharge: storm design memorandum, certificate of conformance during construction and a P.Geo groundwater quality and quantity management program [vaughan.ca]
How do you submit it?
- Apply and pay online through the Service Vaughan portal; all major credit cards are accepted [vaughan.ca].
- Apply separately to York Region through the York sewer use portal [vaughan.ca].
What are the fees?
2026 fee: $2,030 for a dewatering discharge permit and $1,310 for an extension (Fees and Charges By-law 051-2026) [vaughan.ca]. A sampling fee applies on confirmed non-compliance, and sanitary discharges carry a volumetric charge that is invoiced [vaughan.ca].
Official pages
- Dewatering discharge approval
- Discharge approval questions and answers
- Sewer Use By-law
- Sewer Use By-law 025-2024, consolidated (PDF)
- York Region sewer use portal
- Fees and Charges By-law 051-2026 (PDF)
Track Dewatering Discharge Approval (Vaughan) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.