Development Encroachment Agreement: Tie-backs, Shoring and Hoarding (Vaughan)
Encroachment approval under Road Allowance By-law 126-2024 for tie-backs, shoring or hoarding in the City road allowance, with Development Encroachment fees set in Development Engineering's fee schedule [vaughan.ca].
Why is it needed?
- Under Road Allowance By-law 126-2024, an encroachment permit is needed for anything more than 20 cm below ground and for significant encroachments such as commercial ones [vaughan.ca].
- Encroachment permit applications go to By-law and Compliance, Licensing and Permit Services, while the Development Encroachment fees sit in Development Engineering's schedule of the Fees and Charges By-law [vaughan.ca].
When should you apply?
- Get the encroachment approval before the tie-backs, shoring or hoarding go into the road allowance [vaughan.ca].
- Construction work, digging into the road or a construction waste bin in the road allowance needs a separate Road Occupancy Permit [vaughan.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Development Encroachment application [vaughan.ca]
How do you submit it?
- By-law and Compliance, Licensing and Permit Services, which takes encroachment permit applications: bylaw@vaughan.ca, 905-832-2281 [vaughan.ca].
- Development Engineering, whose fee schedule sets the Development Encroachment fees: DEpermits@vaughan.ca, 905-832-2281 [vaughan.ca].
What are the fees?
2026 fee: $6,454.50 for a Development Encroachment application, $13.35 per lineal metre for a tie-back encroachment and $21.50 per lineal metre for a hoarding encroachment (Fees and Charges By-law 051-2026) [vaughan.ca]. For a shoring encroachment, see the City's 2026 Fees and Charges By-law 051-2026 [vaughan.ca].
Forms and guides
- Vaughan Road Allowance By-law 126-2024 (consolidated) (City of Vaughan, by-law)
Official pages
- Road Allowance By-law 126-2024 (PDF)
- Encroachment permits
- Road permits
- Fees and Charges By-law 051-2026 (PDF)