Permit Library › Other GTA municipalities › City of Vaughan › Building permits (Building Standards)
Demolition Permit: House or Part 9 Residential Building (Vaughan)
Demolition permit under Vaughan Building By-law 168-2024, charged at the Part 9 residential demolition rate [vaughan.ca].
You need it when: You demolish a house or another Part 9 residential building in Vaughan.
Why is it needed?
- The Building Code Act, 1992 requires a building permit before demolition starts [vaughan.ca].
When should you apply?
- Get a Heritage Clearance from the City's Cultural Heritage division before applying, because it is required before any demolition permit is issued [vaughan.ca].
- A property that is designated or in a Heritage Conservation District also needs a Heritage Review and Heritage Permit for demolition [vaughan.ca].
- A listed heritage property that is not designated is still protected against demolition under Part IV of the Ontario Heritage Act [vaughan.ca].
- Vaughan Fire and Rescue Service may use a vacant building for training before demolition through its Acquired Structure Program [vaughan.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Online Permitting Portal / ePlans Portal, eservices.vaughan.ca [vaughan.ca]
- Heritage Clearance form with one copy of a survey or site plan identifying the building, with Cultural Heritage approval sought through CulturalHeritage@vaughan.ca [vaughan.ca]
- A copy of the Cultural Heritage approval [vaughan.ca]
- Survey or site plan identifying the building [vaughan.ca]
- Commonly Used Applicable Laws and Building Permits form and Building Permit Applicant Authorization Form, plus the Schedule 1 Designer Information Form and General Review Commitment Form as required [vaughan.ca]
- A professional engineer's report and plans on the demolition method or sequence, where required [vaughan.ca]
How do you submit it?
- Apply on the City of Vaughan Online Permitting Portal / ePlans Portal at eservices.vaughan.ca [vaughan.ca]
- Building Standards: buildingstandards@vaughan.ca, 905-832-8510; building permit application questions: AE@vaughan.ca [vaughan.ca]
What are the fees?
2026 fee: $355 per building for demolition of a Part 9 residential building (Fees and Charges By-law 051-2026) [vaughan.ca].
Forms and guides
- Vaughan Building By-law 168-2024 (City of Vaughan, by-law)
Official pages
- Demolition permit applications
- Heritage review, permits and clearances
- Building By-law 168-2024
- Fees and Charges By-law 051-2026
Track Demolition Permit: House or Part 9 Residential Building (Vaughan) free.