Draft Plan of Condominium (Vaughan)
Draft plan of condominium approval under section 51 of the Planning Act and section 9(2) of the Condominium Act, processed by Development and Parks Planning and decided by Council [vaughan.ca].
You need it when: You are creating a standard, common elements, phased, vacant land or leasehold condominium in Vaughan.
Why is it needed?
- The draft plan shows the units and common elements with a plan of survey [vaughan.ca].
- Rental buildings need no condominium application [vaughan.ca].
- Section 51(34) of the Planning Act applies to draft plans of condominium through section 9 of the Condominium Act, 1998, so you may appeal if no decision is made within 120 days after the application is received [ON].
When should you apply?
- A pre-application consultation (PAC) meeting is needed only for vacant land condominium applications [vaughan.ca].
- The City sends a Notice of Complete Application to the landowner within 30 days of receipt, or a Notice of Incomplete Application within 30 days [vaughan.ca].
- For a vacant land condominium, public notice goes out within 15 days after that, and a notification sign stays up until 7 days after the final decision [vaughan.ca].
- There is no Public Meeting; a Technical Report goes to Committee of the Whole and then Council [vaughan.ca].
- Development Planning prepares the Condominium Agreement from the draft approval conditions [vaughan.ca].
- The Notice of Decision goes out within 15 days of Council's decision and starts a 20-day appeal period; with no appeal, draft approval is in force from the approval date [vaughan.ca].
How long does review take?
Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34), applied by the Condominium Act, 1998 s. 9 [ON]
What documents does a complete application need?
- Development Application Form, commissioned, which the City requires for all Planning Act applications [vaughan.ca]
- GIS Conformity Letter, which Planning GIS and Analytics emails back after you send your georeferenced digital drawings before the formal submission [vaughan.ca]
- Draft plan of condominium showing units and common elements, with a plan of survey [vaughan.ca]
- Condominium Conversion Acknowledgement form (February 2025), for a conversion [vaughan.ca]
How do you submit it?
- Online through the Citizen Service Online Portal, which receives Planning Act applications; let the Planning Technician know when you submit [vaughan.ca].
- Pay the fee by cheque to the City, delivered to the City Hall Welcome Desk or mailed; the application is not processed until the cheque is received and the fee confirmed [vaughan.ca].
- Development and Parks Planning: developmentplanning@vaughan.ca, 905-832-2281, City Hall Level 200 [vaughan.ca].
What are the fees?
2026 fee: $48,243 base for a draft plan of condominium (Fees and Charges By-law 051-2026) [vaughan.ca]. 2026 fee: $19,745 for a revision and $2,998 for an extension (Fees and Charges By-law 051-2026) [vaughan.ca].
Forms and guides
- Vaughan Development Planning Application form (July 2023) (City of Vaughan, application form)
Official pages
- Draft Plan of Condominium application
- Development application submission process
- Development Application Form (PDF)
- 2026 Development Application Fee Calculator
- Fees and Charges By-law 051-2026 (PDF)
Track Draft Plan of Condominium (Vaughan) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.