Building Permit: Small Building, Part 9 (Vaughan)
Building permit under Vaughan Building By-law 168-2024 for a Part 9 building other than a house, applied for through the City's industrial, commercial and institutional permit applications [vaughan.ca].
You need it when: You build, add to or alter a small commercial, industrial or institutional building, a stacked townhouse block or a farm building in Vaughan that falls under Part 9 of the Building Code.
Why is it needed?
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- Other applicable laws, such as zoning, site plan approval, a TRCA permit or a Ministry of Transportation permit near a provincial highway, must be satisfied before a building permit [vaughan.ca].
When should you apply?
- All of Vaughan is a site plan control area, and the landowner must enter into a Site Plan Agreement or Letter of Undertaking with the City before a building permit is issued, subject to exceptions [vaughan.ca].
- Submit the site plan application well before the building permit application, because a Site Plan Agreement must be registered on title before the building permit [vaughan.ca].
- The Building Code decision period starts only once an application is complete [ON]. The City's standard forms include an Acknowledgement of Incomplete Application Form [vaughan.ca].
- If you need to start part of the work before the full permit issues, ask about a conditional or partial permit (Building By-law 168-2024 s. 5.0(14) to (20)) [vaughan.ca].
How long does review take?
Plan for about 15 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Online Permitting Portal / ePlans Portal, eservices.vaughan.ca [vaughan.ca]
- 2024 Ontario Building Code Data Matrix form for Part 9, or the Part 2 form for a farm building [vaughan.ca]
- Land and Building Use Declaration and Structural Statement of Design [vaughan.ca]
- Commonly Used Applicable Laws and Building Permits form, Building Permit Applicant Authorization Form and Schedule 1 Designer Information Form [vaughan.ca]
- Non-residential Plumbing Data Form and the SB-10 energy efficiency checklist for Part 9 [vaughan.ca]
- For a block townhouse project, the City's Applicant Guide for the streamlined Block Townhouse Building Permit process [vaughan.ca]
How do you submit it?
- Apply on the City of Vaughan Online Permitting Portal / ePlans Portal at eservices.vaughan.ca [vaughan.ca]
- Building Standards: buildingstandards@vaughan.ca, 905-832-8510; building permit application questions: AE@vaughan.ca [vaughan.ca]
What are the fees?
2026 fee: $23.84 per m2 for multi-unit and stacked townhouses (Fees and Charges By-law 051-2026) [vaughan.ca]. For commercial, industrial, institutional and farm buildings, see the City's 2026 Fees and Charges By-law 051-2026 [vaughan.ca].
Forms and guides
- Vaughan Building By-law 168-2024 (City of Vaughan, by-law)
- Vaughan Permitting Portal applicant manual (building permits) (City of Vaughan, guide)
Official pages
- Industrial, commercial and institutional permit applications
- Site development (site plan) application
- Applicable laws before a building permit
- Building permit forms, fees and portal manuals
- Fees and Charges By-law 051-2026
Track Building Permit: Small Building, Part 9 (Vaughan) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.