Building Permit: New House, Addition or Secondary Suite (Vaughan)
Building permit under Vaughan Building By-law 168-2024 for a new house, an addition, or a renovation that adds a secondary suite, issued by Building Standards [vaughan.ca].
You need it when: You build a new house, add to an existing house, or renovate a house to create a secondary suite in Vaughan.
Why is it needed?
- A building permit is required when building a new house or adding an addition or alteration to a home [vaughan.ca].
- A new secondary suite, or one built after July 14, 1994, needs a building permit with professionally prepared drawings (architect, engineer or qualified designer) showing Building Code compliance [vaughan.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
- Before applying, make sure the proposal meets the Zoning By-law; while By-law 001-2021 is under appeal, applications not transitioned under its s. 1.6 must comply with both 001-2021 and 1-88 [vaughan.ca].
When should you apply?
- For a new house on an existing lot (infill), get the Grading Permit from Development Engineering before you apply for the building permit [vaughan.ca].
- For an addition, get a grading permit from Development Engineering before you apply for the building permit [vaughan.ca].
- In a new subdivision, the subdivision grading permit from Development Engineering is issued before the building permit application [vaughan.ca].
- A secondary suite needs its own building permit, including when you finish a basement or add a basement walkout [vaughan.ca].
- For a secondary suite, contact Building Standards first for zoning and permit requirements [vaughan.ca]. A suite is allowed only in certain single detached, semi-detached and street townhouses, needs one extra parking space on a surfaced driveway, garage or carport, and is not allowed in the Woodbridge Special Policy Area or a floodplain [vaughan.ca].
- A renovator you hire for a secondary suite must hold a City of Vaughan business licence [vaughan.ca].
- Other applicable laws may apply, such as a TRCA permit in a regulated area, heritage consent for a designated property, or a minor variance from the Committee of Adjustment where the proposal does not meet zoning [vaughan.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on the Online Permitting Portal / ePlans Portal, eservices.vaughan.ca [vaughan.ca]
- Construction drawings by a qualified designer, or by the owner, fully dimensioned, signed and dated, with the designer's name, registration number and BCIN where a designer prepares them [vaughan.ca]. Secondary suite drawings must be professionally prepared [vaughan.ca].
- Site plan, foundation, floor and framing, roof plan, elevations, sections and details, plus engineered truss, floor joist and beam specifications where they apply [vaughan.ca]
- Commonly Used Applicable Laws and Building Permits form, Building Permit Applicant Authorization Form and Schedule 1 Designer Information Form [vaughan.ca]
- Energy Efficiency Design Summary Form (SB-12), mechanical layout with heat loss or gain calculations, and Residential Plumbing Data Form [vaughan.ca]
- Infill Grading Permit from Development Engineering for a new house on an existing lot; 2026 fee: $1,003 plus a $10,000 refundable security deposit (Fees and Charges By-law 051-2026) [vaughan.ca]
- Grading permit from Development Engineering for an addition; 2026 fee: $1,003 over 40 m2 or $693 under 40 m2 (Fees and Charges By-law 051-2026) [vaughan.ca]. The City's grading permit page also lists a $5,000 or $2,500 security deposit [vaughan.ca].
- Subdivision grading permit for a house in a new subdivision; 2026 fee: $630 for singles and semis, $384 per unit for street towns (Fees and Charges By-law 051-2026) [vaughan.ca]
- Construction (infill) tree permit if trees of 20 cm diameter or more are removed or injured; 2026 fee: $360.50 for one tree and $178.27 for each additional tree (Fees and Charges By-law 051-2026) [vaughan.ca]
- TRCA approval, sewage system installer information and septic design, where they apply [vaughan.ca]
- For a suite built before July 14, 1994, a Vaughan Fire and Rescue Service Ontario Fire Code inspection [vaughan.ca]
How do you submit it?
- Apply on the City of Vaughan Online Permitting Portal / ePlans Portal at eservices.vaughan.ca [vaughan.ca]
- Building Standards: buildingstandards@vaughan.ca, 905-832-8510; building permit application questions: AE@vaughan.ca [vaughan.ca]
What are the fees?
2026 fee: $21.82 per m2 for a single dwelling unit including a secondary unit, and $23.84 per m2 for semis and towns, with a $195 minimum (Fees and Charges By-law 051-2026) [vaughan.ca]. For additions and alterations, see the City's 2026 Fees and Charges By-law 051-2026 [vaughan.ca].
Forms and guides
- Vaughan Building By-law 168-2024 (City of Vaughan, by-law)
- Vaughan Permitting Portal applicant manual (building permits) (City of Vaughan, guide)
- Vaughan Secondary Suites information guide for homeowners (Nov 2022) (City of Vaughan, guide)
Official pages
- Building permits for new houses and additions
- How to get a secondary suite
- Residential infill construction
- New subdivision development grading permits
- Fees and Charges By-law 051-2026
Track Building Permit: New House, Addition or Secondary Suite (Vaughan) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.