Permit Library › Other GTA municipalities › Township of Uxbridge › Planning applications and Committee of Adjustment (Development Services)
Draft Plan of Subdivision (Uxbridge)
Approval of a draft plan of subdivision under section 51 of the Planning Act, applied for through Township of Uxbridge Development Services [ON].
You need it when: You want to divide land in Uxbridge into lots or units through a draft plan of subdivision.
Why is it needed?
- Section 51 of the Planning Act sets out draft plan approval and lets you appeal to the Ontario Land Tribunal if the approval authority does not decide in time [ON].
- Subdivision is one of the planning application types on the Township's Development and Planning page [uxbridge.ca].
When should you apply?
- Book a pre-consultation meeting before you submit, and send the pre-consultation form with your request [uxbridge.ca].
- The Permit Fees page also lists Pre-servicing and Grading Plan Approval (residential lots), so ask Development Services whether your subdivision needs them [uxbridge.ca].
How long does review take?
Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34) [ON]
What documents does a complete application need?
- Pre-consultation form, sent with your pre-consultation request [uxbridge.ca]
How do you submit it?
- Email Development Services staff for how to submit a subdivision application, as the Development and Planning page directs [uxbridge.ca].
What are the fees?
Fees on the Township's Permit Fees page, no year shown, plus all external costs: 10 lots or units or less $9,856 plus $477 per lot, 11 to 100 $18,763 plus $477 per lot in excess of 10, and 101 or more $27,752 plus $477 per lot in excess of 10 [uxbridge.ca]. Plan revision $3,588 and pre-consultation $769 [uxbridge.ca].
Forms and guides
- Uxbridge Development Charges By-law (Township of Uxbridge, by-law)
- Uxbridge Pre-consultation Form (Township of Uxbridge, application form)
Official pages
Track Draft Plan of Subdivision (Uxbridge) free.