Draft Plan of Subdivision (Uxbridge)

Approval of a draft plan of subdivision under section 51 of the Planning Act, applied for through Township of Uxbridge Development Services [ON].

You need it when: You want to divide land in Uxbridge into lots or units through a draft plan of subdivision.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 86 business days. Planning Act, R.S.O. 1990, c. P.13, s. 51(34) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

Fees on the Township's Permit Fees page, no year shown, plus all external costs: 10 lots or units or less $9,856 plus $477 per lot, 11 to 100 $18,763 plus $477 per lot in excess of 10, and 101 or more $27,752 plus $477 per lot in excess of 10 [uxbridge.ca]. Plan revision $3,588 and pre-consultation $769 [uxbridge.ca].

Forms and guides

Official pages

Track Draft Plan of Subdivision (Uxbridge) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.