Permit Library › Municipal: City of Toronto › Toronto Water & Engineering & Construction Services › Connections & hydrants
Storm Connection Exemption
Toronto Water exemption under the Sewers By-law, Municipal Code Chapter 681, which otherwise does not permit storm connections to City storm or combined sewers [toronto.ca].
You need it when: Work in Toronto adds a new storm connection to a City sewer, makes one larger, moves one to a different sewer, or replaces one because the building is substantially demolished or rebuilt.
Why is it needed?
- Under the Sewers By-law, storm connections to City storm or combined sewers are not permitted without an exemption, which may be given where there is a hazard or on-site management is not feasible [toronto.ca].
- A building permit does not exempt the owner from applying, and applying does not guarantee approval [toronto.ca].
- A building counts as substantially demolished when more than 50 per cent of the first-storey exterior walls are removed [toronto.ca].
When should you apply?
- Get the exemption and the required building permits before exterior plumbing work starts on private property [toronto.ca].
- It is not needed when Development Review handles the project through a planning application such as Site Plan Control, or when Engineering Transit Review handles it [toronto.ca].
How long does review take?
Plan for about 30 business days. City guidance [toronto.ca]
What documents does a complete application need?
- Municipal Services Application Form [toronto.ca]
- Stormwater management report by a P.Eng. [toronto.ca]
- Servicing report by a P.Eng. [toronto.ca]
- Site storm connection plan at 1:100 [toronto.ca]
- Site topographic survey by a qualified surveyor [toronto.ca]
- Owner authorization letter, if an agent applies [toronto.ca]
How do you submit it?
- Email the Municipal Services Application Form to the Toronto Water Counter at TWC@toronto.ca, then send the supporting documents when staff ask for them [toronto.ca].
- Staff arrange payment of the technical review fee, and Toronto Water issues an approval letter with the approved report and drawings [toronto.ca].
- Toronto Water's Planned Contracts Unit installs the connection in the right-of-way at the owner's expense [toronto.ca].
What are the fees?
A Toronto Water technical review fee applies, listed on the City's water rates and fees page [toronto.ca].
Forms and guides
- Toronto Municipal Code Chapter 681: Sewers (City of Toronto, by-law)
Official pages
Track Storm Connection Exemption free.