Reverse Slope Driveway Technical Review
Toronto Water technical review of a reverse slope driveway, which Zoning By-law 569-2013 prohibits for houses unless a minor variance or rezoning allows it [toronto.ca].
You need it when: You plan a garage with a reverse slope driveway for a detached, semi-detached or townhouse unit in Toronto, and a variance, rezoning or storm connection calls for a Toronto Water review.
Why is it needed?
- Zoning By-law 569-2013 prohibits garages with reverse slope driveways for detached, semi-detached and individual townhouse units, so an exemption is needed through a minor variance or a zoning by-law amendment [toronto.ca].
- The Toronto Water review is needed when a Committee of Adjustment or Ontario Land Tribunal decision requires it, when the City asks for it in a rezoning, or when a storm connection is proposed [toronto.ca].
- A storm connection needs a flap gate backwater valve, a sump pump and an adjacent storm sewer with capacity [toronto.ca].
When should you apply?
- Get the minor variance or zoning by-law amendment approval first, then the Toronto Water technical review, then the building permit [toronto.ca].
- If a storm connection is proposed, include a Storm Connection Exemption Application [toronto.ca].
How long does review take?
Plan for about 30 business days. City guidance [toronto.ca]
What documents does a complete application need?
- Municipal Services Application Form [toronto.ca]
- Topographic survey by a qualified surveyor [toronto.ca]
- Reverse slope driveway report and design drawings by a P.Eng. [toronto.ca]
- Committee of Adjustment conditional approval or Ontario Land Tribunal decision, if applicable [toronto.ca]
How do you submit it?
- Email the Municipal Services Application Form to the Toronto Water Counter at TWC@toronto.ca, then send the supporting documents when staff ask for them [toronto.ca].
- Staff arrange payment of the technical review fee, and Toronto Water issues an approval letter at the end of the review [toronto.ca].
What are the fees?
A Toronto Water technical review fee applies, listed on the City's water rates and fees page [toronto.ca].
Forms and guides
- Toronto Municipal Code Chapter 681: Sewers (City of Toronto, by-law)
Official pages
- Toronto Water reviews for reverse slope driveways
- Committee of Adjustment forms and fees
- Storm connection exemption application
Track Reverse Slope Driveway Technical Review free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.