Conditional Building Permit
A building permit issued before all approvals are in, at the Chief Building Official's discretion under Building Code Act section 8(3) and Municipal Code Chapter 363 [toronto.ca].
You need it when: Work on a larger Toronto development needs to start before every approval is in place, and the full building permit application is already complete.
Why is it needed?
- A conditional permit lets construction start before all approvals are received, mainly on larger developments [toronto.ca].
- It is not a fast track system, and no one has a right to obtain one [toronto.ca].
- The owner signs a conditional permit agreement and bears all risk, including removal of the work and restoration of the site [toronto.ca].
When should you apply?
- Apply only after the full building permit application is complete and zoning complies, including removal of any holding provision [toronto.ca].
- An above-grade conditional permit needs the Site Plan Notice of Approval Conditions (NOAC), and the agreement gives 12 months to get outstanding approvals and 60 days to seriously start construction [toronto.ca].
- Requests are not considered within 30 days of a scheduled increase to development charges [toronto.ca].
How long does review take?
Plan for about 21 business days. City guidance [toronto.ca]
What documents does a complete application need?
- Written conditional permit request: reasons for the delay, scope, unmet applicable laws and the steps to resolve them [toronto.ca]
- Construction schedule with a letter from the general contractor [toronto.ca]
- Proof that the conditional permit requirements are met [toronto.ca]
- Application for a Permit to Construct or Demolish for the conditional permit [toronto.ca]
- Signed conditional permit agreement, which may be registered on title at the owner's expense [toronto.ca]
- Site Plan NOAC from City Planning for an above-grade conditional permit [toronto.ca]
How do you submit it?
- First discuss the request with the Manager of Plan Examination in your Toronto Building district, then send the written request [toronto.ca].
- Once the Plan Review Manager confirms the application can be accepted, file the Application for a Permit to Construct or Demolish [toronto.ca].
What are the fees?
2026 Building Permit Fees page: an additional 10% of full permit fees, minimum $309.31, maximum $3,092.98, non-refundable [toronto.ca]. All fees, including conditional permit fees, must be paid before the permit is issued [toronto.ca].
Forms and guides
- Toronto Municipal Code Chapter 363: Building Construction and Demolition (City of Toronto, by-law)
Official pages
Track Conditional Building Permit free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.