Minor Variance (Scugog)
A minor variance from the Zoning By-law, decided by the Township of Scugog Committee of Adjustment at a hearing under section 45 of the Planning Act [ON].
You need it when: Your Scugog project does not meet a standard in the Township's Zoning By-law and you want a minor variance from the Committee of Adjustment.
Why is it needed?
- Section 45 of the Planning Act has the Committee of Adjustment hold a hearing on each minor variance application [ON].
- Building staff review building permit plans against the Building Code, the Building By-law and other by-laws [scugog.ca].
When should you apply?
- Building staff review permit plans against the Building Code, the Building By-law and other by-laws, so get this approval before you apply for the building permit [scugog.ca].
- If the change is not minor, the route is a Zoning By-law Amendment decided by council under section 34 of the Planning Act [ON].
How long does review take?
Plan for about 21 business days. Planning Act, R.S.O. 1990, c. P.13, s. 45 [ON]
How do you submit it?
- Apply to the Township's Committee of Adjustment, described on its Committee of Adjustment page [scugog.ca].
- Planning Services takes email at planning@scugog.ca [scugog.ca].
What are the fees?
Set in the Tariff of Planning Fees, By-law 17-24 Schedule A. The Fees and Charges page posts no PDF of it, so ask Planning Services for the current fee [scugog.ca].
Official pages
Track Minor Variance (Scugog) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.