Permit Library › Other GTA municipalities › Township of Scugog › Building permits (Building Department)
Designated Structure Permit: Retaining Wall, Telecommunication Tower or Solar Panels (Scugog)
Building permit from the Township of Scugog under Building By-law 18-24 for a designated structure such as a retaining wall, a telecommunication tower or solar panels [scugog.ca].
You need it when: You build a retaining wall, a telecommunication tower or a solar panel installation in Scugog.
Why is it needed?
- The Township lists retaining wall permits among its building permit types [scugog.ca].
- The Ontario Building Code, O. Reg. 163/24, has its own rules for designated structures [ON].
- The Required Building Fees 2026 set separate fees for retaining walls, telecommunication towers and solar panels [scugog.ca].
When should you apply?
- Get the permit before construction starts [scugog.ca].
- The Building Permits page lists a Conservation Authority permit and MTO approval among other approvals that may be needed [scugog.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Building permit application on Cloudpermit [scugog.ca]
- Township approved site plan [scugog.ca]
- Construction plans and other required plans [scugog.ca]
- Schedule 1 Designer Information form [scugog.ca]
- Owner's Authorization form when the applicant is not the owner [scugog.ca]
How do you submit it?
- Apply online through Cloudpermit with the Township of Scugog as the location, or file a paper application at the Township Office [scugog.ca].
- Building Department: 905-985-7346 ext. 169, bdepartment@scugog.ca [scugog.ca].
What are the fees?
2026 fees: retaining walls $15.18 per linear metre, telecommunication towers $781.36 flat fee, and solar $187.85 flat fee plus $15.97 per panel (Required Building Fees 2026) [scugog.ca].
Forms and guides
- Scugog Building By-law 18-24 (Township of Scugog, by-law)
- Scugog Required Building Fees 2026 (Township of Scugog, fee schedule)
- Scugog Building Permit Requirements (Township of Scugog, checklist)
- Scugog How to Submit a Building Permit Application (Township of Scugog, guide)
- Scugog Owner's Authorization Form (Township of Scugog, application form)
- Scugog Schedule 1: Designer Information (Township of Scugog, application form)
Official pages
Track Designated Structure Permit: Retaining Wall, Telecommunication Tower or Solar Panels (Scugog) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.