Permit Library › Other GTA municipalities › Township of Scugog › Building permits (Building Department)
Building Permit: Complex Building, High-rise or High-hazard (Scugog)
Building permit under Scugog Building By-law 18-24 for a complex building. The Township publishes no separate process, so it follows the general application [scugog.ca].
You need it when: You build a high building, a post-disaster building or a high-hazard industrial building in Scugog.
Why is it needed?
- The Building Code treats post-disaster buildings, high buildings and high-hazard industrial buildings as complex buildings [ON].
- No person can construct or demolish a building without first getting a permit from the Township [scugog.ca].
- The Building Department reviews the plans against the Building Code, the Building By-law, other by-laws and fire safety regulations [scugog.ca].
When should you apply?
- The Township lists a Health Department permit, a conservation authority permit, a water or sewer connection permit and MTO approval as possible prerequisites, so line up any that apply before you apply [scugog.ca].
- Once the completed application is received you are invoiced and pay the fees, then revise the application based on Township feedback [scugog.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Township approved site plan [scugog.ca]
- Construction plans and other required plans, such as HVAC, EEDs and truss plans [scugog.ca]
- Schedule 1 Designer Information [scugog.ca]
- Commitment to General Review form [scugog.ca]
- Owner's Authorization Form when someone other than the owner applies [scugog.ca]
- Regional and School Board non-residential development charge forms where development charges apply [scugog.ca]
How do you submit it?
- Apply online through Cloudpermit, keeping the Township of Scugog as the location, or bring a paper application to the Township Office [scugog.ca].
- Building Department: 905-985-7346 ext. 169, bdepartment@scugog.ca [scugog.ca].
What are the fees?
2026 fees per m2 of gross floor area: $28.11 for Group A or B, $20.43 for Group D or E, and $12.47 for other industrial buildings, with a $367.44 minimum (Required Building Fees 2026) [scugog.ca]. Development charges may also apply [scugog.ca]. Online card payments through Paymentus carry a 2.89% service fee [scugog.ca].
Forms and guides
- Scugog Building By-law 18-24 (Township of Scugog, by-law)
- Scugog Required Building Fees 2026 (Township of Scugog, fee schedule)
- Scugog Building Permit Requirements (Township of Scugog, checklist)
- Scugog How to Submit a Building Permit Application (Township of Scugog, guide)
- Scugog Owner's Authorization Form (Township of Scugog, application form)
- Scugog Schedule 1: Designer Information (Township of Scugog, application form)
- Scugog Township Development Charge Form (Township of Scugog, application form)
Official pages
Track Building Permit: Complex Building, High-rise or High-hazard (Scugog) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.