Record of Site Condition (RSC)
A filing in the MECP Environmental Site Registry, prepared by a Qualified Person, summarizing site conditions after Phase One/Two Environmental Site Assessments and any remediation.
You need it when: Land changes to a more sensitive use (e.g. industrial to residential or parkland), or the City/building inspector requires it.
Why it's needed
- Required by O. Reg. 153/04 before a building permit can be issued for a change to a more sensitive land use.
- Toronto Building may request the RSC before occupancy.
When to apply
- Plan early: Phase One and Two ESAs and remediation can take months.
Review time
Documents for a complete application
- Phase One and Phase Two Environmental Site Assessments
- Remediation and/or risk assessment reports (if required)
- RSC filed by a Qualified Person
How to submit
- MECP Environmental Site Registry (online).
Official pages
Track Record of Site Condition (RSC) free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.