Permit Library › Other GTA municipalities › City of Richmond Hill › Building permits (Building Division)
Tent or Temporary Building Permit (Richmond Hill)
Temporary Tent building permit under Richmond Hill Building By-law 19-24, where permits for temporary buildings expire after 180 days [richmondhill.ca].
You need it when: You put up a tent or other temporary building in Richmond Hill.
Why is it needed?
- The Building Permits page says new buildings, including temporary ones, need a permit [richmondhill.ca].
- Permits for temporary buildings expire after 180 days under Building By-law 19-24 s. 4.6(8) [richmondhill.ca].
When should you apply?
- For a community festival or event, the City's Festivals and Events Application must be in at least 90 days before it starts [richmondhill.ca].
- The City says events on City property need Recreation and Culture Division approval through booking@richmondhill.ca [richmondhill.ca].
How long does review take?
Plan for about 10 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish [richmondhill.ca]
- Site plan and drawings as flattened, unprotected PDFs [richmondhill.ca]
- Site map, for a festival or event application [richmondhill.ca]
How do you submit it?
- Apply and pay online through the City's EnerGov Self Service permit portal using the Temporary Tent permit type [richmondhill.ca].
- The permit is issued electronically, and the permit card and drawings must be printed in colour and kept on site [richmondhill.ca].
What are the fees?
Building By-law 19-24 Schedule A Table 3.1 (2026): temporary building (less than 30 days) $462.04 flat, permanent tent or air-supported structure $10.33 per m² [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)
Official pages
Track Tent or Temporary Building Permit (Richmond Hill) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.