Site Plan Approval or Site Plan Amendment (Richmond Hill)

Site plan approval or amendment under Site Plan Control By-law 38-25, as amended by 114-25, and section 41 of the Planning Act, across all of Richmond Hill [richmondhill.ca].

You need it when: You are building non-residential development, more than 10 residential units, or housing on a land lease, shoreline or railway site in Richmond Hill, or changing an approved site plan.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 43 business days. Planning Act, R.S.O. 1990, c. P.13, s. 41(12) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

Fees are set by Tariff of Fees By-law 61-25, with the planning fees in Schedules K, L and M. The fee tables could not be read, so confirm the amount with the City [richmondhill.ca].

Forms and guides

Official pages

Track Site Plan Approval or Site Plan Amendment (Richmond Hill) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.