Permit Library › Other GTA municipalities › City of Richmond Hill › Building permits (Building Division)
Building Permit Revision or Transfer (Richmond Hill)
Revision or transfer of a Richmond Hill building permit, with fees for revisions, house model changes and transfers in Building By-law 19-24 Schedule A [richmondhill.ca].
You need it when: You change the work on a Richmond Hill building permit, or the permit needs to pass to a new owner.
Why is it needed?
- Changes to permitted work are submitted as a revision through the same online form as the original application [richmondhill.ca].
- Building By-law 19-24 provides for transfer of a permit when ownership changes after work has started [richmondhill.ca].
When should you apply?
- Put "Revision to Permit #" and the permit number in the Description of work so the revision is tied to the issued permit [richmondhill.ca].
- A request to defer revocation of an issued permit is due within 30 days of the date on the notice of revocation [richmondhill.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Permit application form with "Revision to Permit #" and the permit number in the Description of work [richmondhill.ca]
- Revised drawings as flattened, unprotected PDFs [richmondhill.ca]
How do you submit it?
- Submit revisions through the City's EnerGov Self Service permit portal on the same form, for example "Revision to Permit #2022-XXXXX" [richmondhill.ca].
What are the fees?
Building By-law 19-24 Schedule A Table 3.8 (2026): permit transfer $210.12, minor revisions (Part 9) hourly with a minimum of $150.18, major revisions (Part 3) hourly with a minimum of $450.59, house model change $348.24 plus the Group C rate per m² of increase [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)
Official pages
- Building permits
- EnerGov Self Service permit portal
- Building permit fees, By-law 19-24 Schedule A (PDF)
Track Building Permit Revision or Transfer (Richmond Hill) free.