Occupancy Permit and Partial Occupancy (Richmond Hill)
Occupancy permit or certificate under Richmond Hill Building By-law 19-24, granted by the City's Building Inspectors once the final inspection is passed [richmondhill.ca].
Why is it needed?
- No one may occupy the building until the final inspection is passed [richmondhill.ca].
- The requirements of both the Fire and Building Departments must be met before the City's Building Inspectors grant occupancy [richmondhill.ca].
- Partial occupancy is available only for ICI, assembly and large residential buildings [richmondhill.ca].
When should you apply?
- For a house, the City must install a water meter before the occupancy certificate, and builders give Revenue Services at least 2 to 4 weeks notice for the meter [richmondhill.ca].
- Deferred City and Region development charges on residential projects other than rental housing are paid before the Occupancy Permit, and on a high rise all of them are due before the first Occupancy Permit [richmondhill.ca].
- Fire protection acceptance test, verification and installation reports go to the Fire Service at least 48 hours before its inspection [richmondhill.ca].
How long does review take?
Plan for about 10 business days. City service standard [richmondhill.ca]
What documents does a complete application need?
- Building Inspection Request form for each inspection [richmondhill.ca]
- Water Meter Installation Form with the building permit number and water meter payment confirmation [richmondhill.ca]
- Fire protection system acceptance test and verification reports [richmondhill.ca]
- Paid City and Region development charges invoice (Invoice 2) for occupancy clearance [richmondhill.ca]
How do you submit it?
- Request each inspection, including the final inspection, on the City's online Building Inspection Request form [richmondhill.ca].
- Request the Fire inspection at 905-883-5444 or fireprevention@richmondhill.ca with the permit number, address, unit number and contact details [richmondhill.ca].
What are the fees?
Building By-law 19-24 Schedule A (2026): occupancy prior to completion (Building Code Div. C 1.3.3) $850.89 under Table 3.5, and re-inspection of unremedied or incomplete work $127.69 per inspection under Table 3.8 [richmondhill.ca]. A Plumbing Not Ready charge of $108.00 residential or $132.00 non-residential applies when the plumbing is not ready for the water meter [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)