Fire Protection Systems Permit: Sprinklers, Fire Alarm or Mag-locks (Richmond Hill)
Building permit under Richmond Hill Building By-law 19-24 for sprinkler, fire alarm and electromagnetic lock work, with Fire Prevention inspecting where the permit requires it [richmondhill.ca].
Why is it needed?
- The Building Permits page lists installing or modifying sprinklers or a fire alarm as work that needs a permit [richmondhill.ca].
- Fire Prevention inspects fire protection systems built under a building permit, such as fire alarms, sprinklers, standpipes and hood suppression [richmondhill.ca].
- Fire and Building requirements must both be met before occupancy is granted [richmondhill.ca].
When should you apply?
- Submit acceptance testing, verification and installation reports to the Fire Service at least 48 hours before its inspection [richmondhill.ca].
- Not every permit needs a Fire inspection, so check the conditions on your permit [richmondhill.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish [richmondhill.ca]
- Sprinkler drawings [richmondhill.ca]
- Schedule 1 Designer Information [richmondhill.ca]
- Acceptance test and verification reports for the Fire inspection [richmondhill.ca]
How do you submit it?
- Apply and pay online through the City's EnerGov Self Service permit portal [richmondhill.ca].
- Request the Fire inspection at 905-883-5444 or fireprevention@richmondhill.ca with the permit number, address, unit number and contact details [richmondhill.ca].
What are the fees?
Building By-law 19-24 Schedule A Table 3.4 (2026): fire alarm Part 9 $349.66, fire alarm Part 3 $229.82 per floor (minimum $476.24), sprinkler $0.46 per m² (minimum $476.24), electromagnetic lock $46.00 each (minimum $546.14) [richmondhill.ca]. There is no Fire fee for the first and second inspections, but later inspections may be charged under the Tariff of Fees By-law [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)
- Richmond Hill Schedule 1: Designer Information (City of Richmond Hill, application form)