Demolition Permit: Non-residential or Part 3 Building (Richmond Hill)

Demolition permit under Richmond Hill Building By-law 19-24 for a non-residential or Part 3 building, applied for with the D1 supplementary form [richmondhill.ca].

You need it when: You demolish a commercial, industrial, institutional or other building in Richmond Hill that is not a Part 9 residential building.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee (Building By-law 19-24 Schedule A): $1,092.29 flat for all occupancies other than Part 9 residential [richmondhill.ca]. Demolishing before a permit adds the greater of $135.82 or 100% of the fee where no application was made, or 25% where one was made [richmondhill.ca].

Forms and guides

Official pages

Track Demolition Permit: Non-residential or Part 3 Building (Richmond Hill) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.