Permit Library › Other GTA municipalities › City of Richmond Hill › Building permits (Building Division)

Conditional or Partial Building Permit (Richmond Hill)

Conditional permit (Building Code Act section 8(3)) with agreements, or a partial permit for part of a project, under Richmond Hill Building By-law 19-24 [richmondhill.ca].

You need it when: You need to start part of a Richmond Hill project, such as a model home or new construction, before the full building permit is issued.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fees (Building By-law 19-24 Schedule A): conditional permit $7,346.11 and extension of the agreement $546.14 (Table 3.8), and partial permit $491.53 per partial permit (Table 3.1) [richmondhill.ca]. A phased permit is $210.12 each [richmondhill.ca].

Forms and guides

Official pages

Track Conditional or Partial Building Permit (Richmond Hill) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.