Permit Library › Other GTA municipalities › City of Richmond Hill › Building permits (Building Division)
Building Permit: Small Building, Part 9 (Richmond Hill)
Non-residential building permit under Richmond Hill Building By-law 19-24 for a new Part 9 building or addition other than a house [richmondhill.ca].
You need it when: You build or add to a small commercial, industrial or institutional building in Richmond Hill that falls under Part 9 of the Building Code.
Why is it needed?
- The Building Division issues non-residential (ICI) permits for new Part 9 and Part 3 buildings and additions [richmondhill.ca].
- Building staff review each application for Building Code, zoning and applicable law [richmondhill.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Where Site Plan Control applies (By-law 38-25 as amended by 114-25), an executed Site Plan Agreement is a pre-approval for the permit [richmondhill.ca].
- New non-residential construction also needs a separate site services (exterior plumbing) permit [richmondhill.ca].
- Development charges on non-residential work must be paid in full before the permit is issued, unless a City deferral policy, such as for some office buildings or charitable non-profits, applies [richmondhill.ca].
How long does review take?
Plan for about 15 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish and Schedule 1 Designer Information [richmondhill.ca]
- C1 Non-Residential Permit and Site Servicing Permit Applications Checklist items [richmondhill.ca]
- Site plan, architectural, structural, mechanical and site services drawings [richmondhill.ca]
- Statement of Design and Commitment to General Review where they apply [richmondhill.ca]
- L1 Applicable Law Declaration, P1 Plumbing and Drain Worksheet and T5 Mechanical Unit Data Sheet [richmondhill.ca]
How do you submit it?
- Apply through the City's EnerGov Self Service portal at permits.richmondhill.ca [richmondhill.ca].
- Building Division: building@richmondhill.ca, 905-771-8810, with zoning questions by email only [richmondhill.ca].
What are the fees?
2026 fees (Building By-law 19-24 Schedule A) are per m2 by occupancy, for example business, personal services and mercantile $21.59 shell or $29.49 finished, and industrial $14.66 shell or $20.97 finished [richmondhill.ca]. The minimum permit fee for non-residential work is $420.24 [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)
- Richmond Hill Schedule 1: Designer Information (City of Richmond Hill, application form)
- Richmond Hill L1 Applicable Law Declaration (City of Richmond Hill, checklist)
- Richmond Hill P1 Plumbing and Drain Worksheet (City of Richmond Hill, application form)
- Richmond Hill C1 Non-Residential Permit and Site Servicing Permit Applications Checklist (City of Richmond Hill, checklist)
Official pages
Track Building Permit: Small Building, Part 9 (Richmond Hill) free.