Why is it needed?
- Building staff review each application for Building Code, zoning and applicable law, and Fire Prevention reviews fire protection [richmondhill.ca].
- The Fire Service inspects fire protection systems under the permit, and both Fire and Building requirements must be met before occupancy [richmondhill.ca].
- The Ontario Building Code, O. Reg. 163/24, applies to the permit in every Ontario municipality [ON].
When should you apply?
- Where Site Plan Control applies (By-law 38-25 as amended by 114-25), an executed Site Plan Agreement is a pre-approval for the permit [richmondhill.ca].
- Other pre-approvals can include a Committee of Adjustment decision, TRCA approval, CNR approval near rail corridors and York Region approval for entrances from Regional roads [richmondhill.ca].
- Non-residential development charges are paid before the permit is issued, and deferred City and Region charges on a residential high-rise are paid before the first occupancy permit [richmondhill.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish and Schedule 1 Designer Information [richmondhill.ca]
- C1 Non-Residential Permit and Site Servicing Permit Applications Checklist items [richmondhill.ca]
- Site plan, architectural, structural, mechanical, sprinkler and site services drawings, plus a soils report where needed [richmondhill.ca]
- Statement of Design and Commitment to General Review by the architect or engineer [richmondhill.ca]
- L1 Applicable Law Declaration, P1 Plumbing and Drain Worksheet and T5 Mechanical Unit Data Sheet [richmondhill.ca]
How do you submit it?
- Apply through the City's EnerGov Self Service portal at permits.richmondhill.ca [richmondhill.ca].
- Building Division: building@richmondhill.ca, 905-771-8810, with zoning questions by email only [richmondhill.ca].
What are the fees?
2026 fees (Building By-law 19-24 Schedule A) are per m2 by occupancy, for example assembly $24.06 shell or $40.95 finished, institutional $33.37 shell or $38.73 finished, and other multi-unit residential $25.86 [richmondhill.ca]. The minimum permit fee for anything other than Part 9 residential work is $420.24 [richmondhill.ca]. Fees over $20,000 may be paid 50% at application and the balance at issuance, and card payments are capped at $100,000 [richmondhill.ca].
Forms and guides
- Richmond Hill Building By-law 19-24, as amended (City of Richmond Hill, by-law)
- Richmond Hill Building By-law 19-24, Schedule A permit fees (2026) (City of Richmond Hill, fee schedule)
- Richmond Hill Application for a Permit to Construct or Demolish (City of Richmond Hill, application form)
- Richmond Hill Schedule 1: Designer Information (City of Richmond Hill, application form)
- Richmond Hill L1 Applicable Law Declaration (City of Richmond Hill, checklist)
- Richmond Hill P1 Plumbing and Drain Worksheet (City of Richmond Hill, application form)
- Richmond Hill C1 Non-Residential Permit and Site Servicing Permit Applications Checklist (City of Richmond Hill, checklist)
Official pages
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.