Site Plan Approval (Pickering)

Site plan approval under section 41 of the Planning Act, made to Pickering City Development and charged under the City's Schedule of Application Fees [pickering.ca].

You need it when: Your Pickering project needs site plan approval from the City under section 41 of the Planning Act.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 43 business days. Planning Act, R.S.O. 1990, c. P.13, s. 41(12) [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fees: $20,000 plus a per-unit fee plus $7,300 per 2,000 m2 of non-residential GFA, and $5,000 for a minor site plan revision (Schedule of Application Fees, July 1, 2026) [pickering.ca].

Forms and guides

Official pages

Track Site Plan Approval (Pickering) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.